We are preparing a budget for a self-build project and have included the land and building costs on a square metre figure basis. What other items should we include?
You should also allow for design fees, local authority connection charges, insurances, external works, scaffolding plant hire costs and hutting. I would also include about 5- 7.5 per cent for a contingency reserve fund.