How does Biodiversity Net Gain impact self builders?
The basic principle of preserving and encouraging biodiverse habitats is something to be encouraged. However, developing and implementing BNG plans can be complex and costly – potentially adding a significant burden that large developers can bear much more easily than self builders.
When you apply to your local planning authority for planning permission for your project, you will need to confirm whether your development is exempt from biodiversity net gain (BNG) – keep scrolling to find out more about exemptions.
If your project isn’t exempt from BNG rules, you’ll have to provide details on how you’re planning on meeting the BNG objective, including information about the site-specific enhancements that you are going to make.

Toby Diggens and Bella Lowes restored and rebuilt a derelict barn in Dorset under the Living Building Challenge, which celebrates the wider setting of a building and its ecological impact. This encouraged them to embrace natural materials and a sensitive design both inside and out, giving back to the environment throughout the build. “We chose mostly native plants, plus European species from similar landscapes, and left some bare ground for solitary bees and blow-ins,” says Toby. Photo: Simon Burt
If your local planning authority grants your project planning permission, you’ll need to put together a comprehensive plan, with supporting evidence, demonstrating how you will achieve the 10% increase in biodiversity. The local planning authority will then either approve or refuse your biodiversity net gain plan within 8 weeks. You won’t be able to start your build until the authority has come to a decision.
This plan must be managed and maintained for 30 years, commencing on the date you complete the development. If you do not meet these requirements, then the local planning authority could take action.
FIND YOUR LOCAL PLANNING AUTHORITY
Which projects are exempt from meeting BNG criteria?
The introduction of biodiversity net gain laws aims to cover the majority of housebuilding developments. However, there are certain exemptions. These include:
- Development projects where the planning application was made before day one of mandatory biodiversity net gain on 12 February 2024.
- Those who are making a householder planning application – which could be for a home extension or conservatory.
- Developments that do not impact a priority habitat and impact less than 25m² of on-site habitat and 5 metres of on-site linear habitats, such as hedgerows.
- Developments that are granted planning permission by a development order (this could be permitted development rights).
- Developments on sites of 0.2 hectares (approx 0.5 acres) or less, provided they do not impact a priority habitat. It’s worth noting that most self build houses would sit comfortably on a plot of 0.5 acres or less.
Biodiversity Net Gain exemptions for self build projects
As of the 6th August 2026, the Biodiversity Net Gain exemption for self build and custom build developments is no longer in valid.
If your planning application was submitted before the 6th August 2026, the previous exemption may still apply under transitional arrangements. Under these rules, bespoke self build homes and small custom build developments were exempt from biodiversity net gain, provided they met the following conditions:
- The development should consist of no more than 9 dwellings.
- The site had an area no larger than 0.5 hectares (approx. 1.2 acres).
- The site consisted exclusively of dwellings that were self build or custom housebuilding as defined in section 1(A1) of the Self-build and Custom Housebuilding Act 2015.